The first installation of the Delta 3900 Nordex turbine in Turkey has been successfully completed. This installation occurred in Suhut, Afyon, at an altitude of 2,200 meters. Our installation team utilized the Ematec blade lifter and the Fieldmann turn drive for the single-blade assembly.
The locally produced blades, measuring 65.5 meters long, were transported along challenging roads at this high altitude. As of 2018, these blades have been the longest Nordex blades in Turkey. We provided a comprehensive range of services for the installation of 10 x N131/3900 turbines, which included transport, crane operation, and installation services.
The N131 blades in the Eber wind farm are expected to generate 136,000 MWh of clean energy.
Power: | 39 MW |
Location: | Afyon, Turkiye |
Date: | 2018 |
Manufacturer: | Nordex |
Scope: | Full Scope TCI (Transport, Crane, Installation) |